Location
District Landfill Dettendorf
Stüberacher Straße 1
D-91456 Diespeck
c. 35 km NW of Nuremberg
Projected and installed by
Seiler Elektrotechnik GmbH
Külsheimer Straße 10
D-91438 Bad Windsheim
www.seiler-gebaeudetechnik.de
Installation
24 tracking systems
central control system, CCU, 1x LCU, remote control
central inverter
Modules: Solara S880 TI
power: 50 KWp
inverter: SolarMax 50C (central inverter)
Foundations
Screw foundation, 3 m deep
Krinner Schraubfundamente GmbH
Passauer Straße 55
D-94342 Straßkirchen
Services by Krinner: insertion of screw foundations
delivery of solar tracking units
assembly of solar tracking units
installation of solar modules
Partnership LORENTZ/Krinner
Schedule of Installation
insertion of screw foundations: 08.-09.12.2005
assembly and installation of tracking units and modules: 12.-16.12.2005
electric connection PV equipment: two days
connected to the grid: 23.12.2005
complete duration of errection: approx. two weeks
 |
Finished Installation
In the Snow
Mounting and Wiring
Assembly of Solar Tracking Units
Screw Connection of the Mounting
 |